Kera-Koticha Asphalt Road Project
about project
Client: Bishoftu City Administration
Contract Period: March 2021 – March 2023 (980 days)
Project Status: Completed
Length: 2.5 km
Project Overview:
The Kera-Koticha Asphalt Road Project represents a major enhancement to Bishoftu’s internal road network. Spanning 2.5 kilometers, this road was constructed to support the city’s growing transportation needs by improving connectivity between residential areas, public services, and commercial routes.
Scope of Work:
ASGC was responsible for the full execution of civil works, including:
- Subgrade excavation and stabilization
- Base course and sub-base construction
- Asphalt concrete paving with precision grading
- Installation of lined side drains for stormwater management
- Integration of road markings and urban safety features such as signage and shoulders
Impact:
The completed road now enables faster commuting and safer vehicle operation, particularly for school buses, delivery trucks, and public transportation. It also supports efficient movement of goods and services across municipal zones, contributing to Bishoftu’s urban development goals. The project showcases ASGC’s ability to deliver high-quality urban roads that meet durability and safety standards.